Project status

From proposal to defensio

A diploma thesis runs across a whole school year. This page states openly what is finished, what we are working on and what is still ahead – including the things that will not work on the first try.

2 of 20 milestones reached · as of September 2026

September 2026done

Proposal and project start

Goal definition, work breakdown structure, stakeholder and risk analysis, a budget of 7,000 euros and the milestone list. The proposal was submitted on 24 September and this website launched the same day. The donor bike is already in the workshop.

October 2026up next

Digitisation and sizing

3D scanning the frame and rebuilding it in CAD, sizing the components with a first battery pack mock-up, specifying the electronics and running initial lab tests.

November 2026open

Mechanical design and motor control

Designing the motor and controller mounts, the pitch presentation to an industry audience, programming and commissioning the motor control.

December 2026open

First test ride and battery pack

The initial test ride with the prototype, in parallel the CAD design of the battery pack plus cell connection and spot welding.

January 2027open

Integration and full-system test ride

Completing the battery pack, integrating drivetrain and display, and finally the full-system test ride – the moment that shows whether 65 km/h and 45 km hold up.

February to May 2027open

Documentation, presentation, defensio

First draft of the written thesis, acceptance, the final presentation of the diploma theses, the corrected copy and, on 21 May 2027, the defensio.

Overview

All 20 milestones

The target dates from the thesis proposal, kept up to date.

# Milestone Target date Status
1Thesis proposal submitted24 Sep 2026done
2Project website launched24 Sep 2026done
3Database entry submitted05 Oct 2026up next
43D scan and digitisation10 Oct 2026open
5Component sizing and battery pack mock-up25 Oct 2026open
6Electronics specification and lab tests25 Oct 2026open
7Motor mount designed05 Nov 2026open
8Controller mount designed15 Nov 2026open
9Pitch presentation of the diploma theses24 Nov 2026open
10Motor control programmed and commissioned25 Nov 2026open
11First test ride (prototype)14 Dec 2026open
12Battery pack designed in CAD14 Dec 2026open
13Cell connection and spot welding28 Dec 2026open
14Battery pack completed06 Jan 2027open
15Drivetrain and display integrated10 Jan 2027open
16Full-system test ride15 Jan 2027open
17First draft of the written thesis08 Feb 2027open
18Thesis accepted05 Mar 2027open
19Final presentation and corrected copy12 Mar 2027open
20Defensio21 May 2027open
@tesmos.htlrennweg Workshop pictures, measurements and everything that breaks along the way. We post at least every three weeks.