Project Status
From Application to Defense
A diploma project runs for a whole school year. Here you can openly see what is finished, what we are currently working on, and what is still pending (including the things that won't work on the first try).
3 of 20 milestones reached · As of October 2026
Application and Project Start
Definition of goals, object breakdown structure, work breakdown structure, stakeholder and risk analysis, budget of 7,200 to 7,700 euros, and the milestone list. The application was submitted on September 24th, this website was launched on the same day. The base vehicle is already in the workshop.
Digitization and Design
3D scan of the frame and remodeling in CAD, component design with an initial battery pack mockup, electronics specification, and first laboratory tests.
Construction and Motor Control
Construction of the motor and motor controller mounts, pitch presentation to a professional audience, programming, and commissioning of the motor control.
First Test Drive and Battery Pack
The initial test drive with the prototype, in parallel the CAD design of the battery pack as well as cell connection and spot welding.
Integration and System Test Drive
Completion of the battery pack, integration of the drivetrain and display, and finally the test drive with the complete system. This is where we'll see if the 65 km/h and 45 km hold up.
Documentation, Presentation, Defense
First draft of the written thesis, approval, final presentation of the diploma projects, correction copy, and on May 21, 2027, the defense.
Overview
All 20 Milestones
The target dates from the project application, continuously updated.
| # | Milestone | Target Date | Status |
|---|---|---|---|
| 1 | Application for admission to diploma project submitted | 24.09.2026 | done |
| 2 | Information website launched | 24.09.2026 | done |
| 3 | Database submitted | 05.10.2026 | done |
| 4 | 3D Scan and Digitization | 10.10.2026 | up next |
| 5 | Component design and battery pack mockup | 25.10.2026 | open |
| 6 | Electronics specification and lab tests | 25.10.2026 | open |
| 7 | Construction of motor mount | 05.11.2026 | open |
| 8 | Construction of motor controller mount | 15.11.2026 | open |
| 9 | Pitch presentation of diploma projects | 24.11.2026 | open |
| 10 | Motor control and commissioning | 25.11.2026 | open |
| 11 | Initial test drive (Prototype) | 14.12.2026 | open |
| 12 | Battery pack design in CAD | 14.12.2026 | open |
| 13 | Cell connection and spot welding | 28.12.2026 | open |
| 14 | Completion of battery pack | 06.01.2027 | open |
| 15 | Integration of drivetrain and display | 10.01.2027 | open |
| 16 | System test drive (Complete System) | 15.01.2027 | open |
| 17 | First draft of the written thesis | 08.02.2027 | open |
| 18 | Diploma thesis approved | 05.03.2027 | open |
| 19 | Final presentation and correction copy | 12.03.2027 | open |
| 20 | Defense | 21.05.2027 | open |